[NOV-3] "ELZ_1 play" UPDATE #9 PCB / Passed FCC and CE certification!

[NOV-3] "ELZ_1 play" UPDATE #9 PCB / Passed FCC and CE certification!

Topics of the Week

<About hardware>

We checked that the board that arrived last Thursday worked properly, and went to take the FCC/CE certification test on Tuesday as scheduled.

We successfully passed the FCC/CE certification exam on Wednesday.

 

< About software >

Firmware testing and debugging work is underway.

 

Schedule for next week

- We will order the 1st batch from the factory.

- Start of 1st batch PCB manufacturing.

- Adjustment of production schedule.

 

Future schedule (under adjustment)

Week of November 27: Assembly of 1st batch begins and testing begins.

Assembly and inspection of the first batch will be completed and shipping will start in order.

 

We will proceed with development as fast as possible, but the schedule may change depending on the development status.

 

Thanks,

Yu Endo

 

 

今週の出来事

<ハードウェアについて>

先週木曜日に到着した基板の一通りの動作チェックを完了し、予定通り火曜日からFCC/CE認証試験を受けに行きました。

水曜日に無事FCC/CE認証試験をパスしました。

 

<ソフトウェアについて>

ファームウェアの検査とデバッグ作業を実施しております。

 

来週の予定

1stロット発注、1stロットの基板製造開始

生産日程の調整

 

今後のスケジュール(調整中)

11月27日の週 1stロットの組み立て開始、検査実施開始

組み立て、検査完了したものから順次発送開始

 

なるべく最速で開発が進むように進めますが、開発状況に応じて日程に変更が生じる可能性があります。

 

遠藤

 