Topics of the Week <About hardware>  At the Malaysian factory, we are currently installing electronic parts and wiring into the case in order from the board that has been completed....

[JAN-12] "ELZ_1 play" UPDATE #15 Shipments will...

Topics of the Week <About hardware>  At the Malaysian factory, we are currently installing electronic parts and wiring into the case in order from the board that has been completed....

[DEC-28] "ELZ_1 play" UPDATE #14 We have started to ship the assembled products to our head office in Japan. / Reference Manual

[DEC-28] "ELZ_1 play" UPDATE #14 We have starte...

Topics of the Week <About hardware> Although the production speed is still slow, we are sequentially proceeding to the process of assembling the boards into the case, starting with those...

[DEC-28] "ELZ_1 play" UPDATE #14 We have starte...

Topics of the Week <About hardware> Although the production speed is still slow, we are sequentially proceeding to the process of assembling the boards into the case, starting with those...

[DEC-22] "ELZ_1 play" UPDATE #13 Assembly and inspection have begun.

[DEC-22] "ELZ_1 play" UPDATE #13 Assembly and i...

Topics of the Week <About hardware> At our factory in Malaysia, we are currently assembling SMT electronic parts and wiring for First Batch. This week, our director went to the...

[DEC-22] "ELZ_1 play" UPDATE #13 Assembly and i...

Topics of the Week <About hardware> At our factory in Malaysia, we are currently assembling SMT electronic parts and wiring for First Batch. This week, our director went to the...

[DEC-8] "ELZ_1 play" UPDATE #12 SMT electronic parts are being installed / Some preset patches for ELZ_1 play.

[DEC-8] "ELZ_1 play" UPDATE #12 SMT electronic ...

Topics of the Week <About hardware> Production of the 1st batch of PCBs has been completed.Those PCBs have arrived at the factory in Malaysia.Currently, SMT electronic parts are being installed...

[DEC-8] "ELZ_1 play" UPDATE #12 SMT electronic ...

Topics of the Week <About hardware> Production of the 1st batch of PCBs has been completed.Those PCBs have arrived at the factory in Malaysia.Currently, SMT electronic parts are being installed...

[NOV-24] "ELZ_1 play" UPDATE #11 We are currently manufacturing the 1st batch of PCB / Some preset patches for ELZ_1 play.

[NOV-24] "ELZ_1 play" UPDATE #11 We are current...

Topics of the Week <About hardware> We are currently manufacturing the 1st batch of PCB. PCB manufacturing will be completed on November 30th, and installation of electronic parts will begin.Assembly...

[NOV-24] "ELZ_1 play" UPDATE #11 We are current...

Topics of the Week <About hardware> We are currently manufacturing the 1st batch of PCB. PCB manufacturing will be completed on November 30th, and installation of electronic parts will begin.Assembly...

[NOV-17] "ELZ_1 play" UPDATE #10 1st batch PCB manufacturing started / Some preset patches for ELZ_1 play.

[NOV-17] "ELZ_1 play" UPDATE #10 1st batch PCB ...

Topics of the Week <About hardware> 1st batch ordered, 1st batch PCB manufacturing started. PCB manufacturing will be completed on November 30th, and installation of electronic parts will begin.Assembly is...

[NOV-17] "ELZ_1 play" UPDATE #10 1st batch PCB ...

Topics of the Week <About hardware> 1st batch ordered, 1st batch PCB manufacturing started. PCB manufacturing will be completed on November 30th, and installation of electronic parts will begin.Assembly is...